Automatic Secondary Degassing & Tail Welding Machine for Heat Pipe

This all-in-one machine integrates four operations into a single automated cycle: secondary degassing, straightening, fixed-length cutting, and TIG tail welding. The vacuum is held continuously from degassing through welding — the pipe never leaves the controlled environment, eliminating the gas re-entry risk that separate stations cannot avoid.

Product Description

Automatic Secondary Degassing, Cutting & Tail Welding Machine for Heat Pipe Production

Four operations in one automated cycle: secondary degassing, straightening, fixed-length tail cutting, and TIG tail welding — with the vacuum held continuously from degas to weld. Replaces 3 standalone stations and 2-3 operators with one machine and one loading position.

Overview

The final sealing sequence is where heat pipe quality is won or lost. After working fluid injection, the pipe must be degassed a second time to drive out residual non-condensable gases, then cut to final tail length and welded shut — and the vacuum must survive every step. On lines using separate stations, the pipe leaves the vacuum environment between degassing and welding. That transfer window is where gas re-entry happens, and it is the single most common root cause when finished heat pipes show degraded performance after weeks in the field.

The CT-SDW-6 closes that window. It integrates secondary degassing, straightening, fixed-length cutting, and TIG tail welding into one automated cycle, with the weld completed while the vacuum is still held. The pipe never leaves the controlled environment between degas and seal. Cycle time is 8–15 seconds per pipe depending on size — 240 to 450 pipes per hour from a single loading position.

Why an All-in-One Machine Instead of Separate Stations

Dimension3 separate stationsAll-in-one machine (CT-SDW-6)
Operators per shift2–31 (loading/unloading only)
Floor space~25–35 m²~8–10 m²
Vacuum exposure between degas and weldPipe leaves vacuum, risk of gas re-entryContinuous — weld happens while vacuum held
Handling damage risk2 manual transfers between stationsZero — automatic transfer inside machine
Cycle consistencyOperator-dependent timingMachine-controlled, ±0.5 sec repeatability
Per-pipe data traceabilityManual records, often incompleteAutomatic logging per pipe

The vacuum continuity row is the one that matters most for quality. Floor space and labor savings recover the investment; vacuum continuity is what removes a failure mode that separate stations cannot eliminate.

Key Features

• 4-in-1 integration — secondary degassing, straightening, fixed-length cutting, and tail welding in one automatic sequence

• Continuous vacuum from degas to weld — ≤ 5 × 10⁻³ Pa held through the entire sequence, eliminating gas re-entry between stations

• 8–15 second cycle time — 240–450 pipes per hour with one operator handling loading only

• TIG welding with process monitoring — current, voltage, and arc duration logged per weld; helium-tight result ≤ 1 × 10⁻⁸ Pa·m³/s

• Tail length accuracy ±0.2mm — servo-positioned cutting for consistent finished length across the batch

• Dedicated programming system — touchscreen HMI with simple recipe editing, data storage and recall by product number

• Per-pipe data logging — vacuum level, weld parameters, and cycle result recorded for every pipe, exportable for customer audits

• Two-frame layout — main machine frame plus separate vacuum pump / hydraulic station frame, keeping pump vibration and heat away from the process zone

• Quick-change tooling — Φ4–Φ10mm pipe range covered with fixture swap in under 15 minutes

Technical Specifications

ParameterValue
ModelCT-SDW-6
Integrated functionsSecondary degassing + straightening + fixed-length cutting + tail welding (4-in-1)
Stations replaced3 standalone stations (degassing, cutting, welding) + 2-3 operators
Compatible pipe diameterΦ4mm – Φ10mm (Φ12mm option)
Compatible pipe length100mm – 600mm
Cycle time8 – 15 seconds per pipe (size dependent)
Throughput240 – 450 pipes per hour
Degassing heating temperature120°C – 160°C (recipe-controlled)
Vacuum level during degassing≤ 5 × 10⁻³ Pa
Tail length after cuttingConfigurable, tolerance ±0.2mm
Welding methodArgon arc welding (TIG) with current/voltage monitoring
Weld leak rate≤ 1 × 10⁻⁸ Pa·m³/s (helium-tight)
Straightening accuracy±0.3mm over pipe length
Control systemPLC + touchscreen HMI, dedicated programming system
Recipe storageUnlimited, with data storage and recall function
Data loggingPer-pipe: vacuum level, weld current, cycle result, timestamp
Frame configurationMain machine frame + separate vacuum pump / hydraulic station frame
Power supply380V / 50Hz / 3-phase, ~15kW
Compressed air0.5 – 0.7 MPa
Machine dimensions~2400 × 1500 × 1900mm (main frame)
ComplianceCE-ready design

Note: parameters above are for the standard CT-SDW-6 configuration. Custom configurations available for Φ12mm pipes, longer pipe ranges, and integration with upstream filling equipment.

How It Works

Stage 1: Loading & Secondary Degassing

The operator loads filled heat pipes (working fluid already injected, primary degassing complete) into the fixture. The machine connects the open tail to the vacuum system and heats the pipe body to the recipe temperature:

✓  Pipe heated to 120–160°C — working fluid boils, driving dissolved gases out of solution

✓  Vacuum system extracts liberated gases through the open tail

✓  Vacuum level monitored in real time; cycle advances only when ≤ 5 × 10⁻³ Pa is reached

✓  Per-pipe vacuum reading logged for traceability

Stage 2: Straightening

While still in the fixture, the pipe passes through the straightening section:

✓  Multi-point correction brings pipe straightness to ±0.3mm

✓  Correction force limited by recipe to protect the sintered wick

✓  No separate handling step — straightening happens inside the machine sequence

Stage 3: Fixed-Length Cutting

The tail is cut to the final product length while vacuum is maintained at the crimp point:

✓  Crimp seal applied below the cut point before the blade contacts the tube

✓  Servo-positioned cut delivers tail length tolerance ±0.2mm

✓  Cut scrap collected automatically; no copper debris at the weld zone

Stage 4: TIG Tail Welding & Unload

The crimped tail tip is fused by TIG arc into a permanent hermetic seal:

✓  Argon-shielded TIG arc fuses the crimped tip — no filler material

✓  Weld current, voltage, and arc duration logged per pipe

✓  Result: helium-tight seal ≤ 1 × 10⁻⁸ Pa·m³/s

✓  Finished pipe ejected to output tray; cycle restarts automatically

Applications

This machine serves the final sealing section of any sintered or mesh wick heat pipe production line: AI server cooler heat pipes, laptop thermal module pipes, EV battery cooling pipes, and LED heat sink pipes. It is the automation upgrade path for factories currently running separate degassing, sealing, and welding stations — and the standard configuration for new lines targeting 240+ pipes per hour. For full line planning context, see our guide on how to set up a heat pipe production line.

Why Choose thermalmachinery

• Full production line scope — we build the equipment for the entire heat pipe process, so this machine arrives with tooling matched to your upstream filling and shrinking stations

• Engineer-led commissioning — on-site installation, recipe tuning on your actual pipes, operator training, 12-month warranty

• Proven in production — our equipment runs in heat pipe factories supplying Foxconn, Nidec, Furukawa Electric, and Samsung supply chains

• Custom configurations — pipe size range, automation level, and upstream integration specified at order time

FAQ

What is secondary degassing and why is it needed?

Primary degassing removes bulk air from the empty pipe before fluid injection. Secondary degassing happens after the working fluid is inside: the fluid is heated so dissolved gases come out of solution and are extracted under vacuum. Skipping it leaves non-condensable gas inside the sealed pipe, which accumulates at the condenser end during operation and degrades thermal performance over weeks to months. It is the most common root cause of field failures that pass initial factory testing.

Yes — that is its purpose. It replaces the standalone secondary degassing station, the cutting station, and the tail welding station, plus the manual transfers between them. Factories typically redeploy 1–2 operators per shift and recover 15–25 m² of floor space. The quality gain comes from vacuum continuity: the pipe never leaves the controlled environment between degas and weld.

Standard configuration covers Φ4mm to Φ10mm diameter and 100mm to 600mm length. A Φ12mm option is available. Changeover between sizes uses quick-change fixtures and takes under 15 minutes including recipe recall.

Two layers. In-process: the machine logs weld current, voltage, and arc duration per pipe and flags any weld outside the recipe window. Post-process: the welded seal achieves ≤ 1 × 10⁻⁸ Pa·m³/s, verified by downstream leak testing. Most customers run 100% pressure-decay leak testing after this machine and helium audit sampling per batch.

The vacuum pump and hydraulic station sit on a separate frame connected by hoses and cables, typically placed 1–2 meters from the main machine. This keeps pump vibration and heat away from the welding zone and makes pump maintenance possible without stopping access to the process area. Total installed footprint including both frames is about 10 m².